Below are representative samplings of completed projects:

Cape Romain completed project image 2 image 3

Ace Basin Parkway Bridges

Beaufort and Colleton Counties, SC
Owner:  SCDOT
Construction Cost: $6,450,000
Completion Date:  October 2010

Details
Cape Romain completed project

Replacement Bridges #49 & #59

Brunswick County, NC
Owner:  NC Department of Transportation
Construction Cost: $1,611,000
Completion Date:  April 2011

Details
Cape Romain completed project

CHS Naval Base Cont. Terminal

Charleston County, SC
Owner:  South Carolina State Ports Authority
Construction Cost: $43,662,000
Completion Date:  September 2010

Details
Cape Romain completed project

Cordesville Railroad Bridge

Berkeley County, SC
Owner:  CSX Corporation
Construction Cost: XXX
Completion Date:  January 2011

Details
Cape Romain completed project

Dolphin Cove Marina

Charleston, SC
Owner Representative:  Envirocon
Construction Cost: $465,000.00
Completion Date:  June 2011

Details
Cape Romain completed project

I-385 Rehab & Bridge Jacking

Greenville County, SC
Owner:  SC Department of Transportation
Construction Cost: $ 656,000.00
Completion Date:  November 2010

Details
Cape Romain completed project image 2 image 3

Morris Island Light

Charleston County, SC
Owner:  Save the Light,
Construction Cost: $734,313
Completion Date:  August 2010

Details
Cape Romain completed project

Box Girder Bridge

Kinston, NC
Owner:  NCDOT
Construction Cost:XXX
Completion Date:  March 2011

Details
Cape Romain completed project

Robert Edge Parkway

Horry County, SC
Owner:  SCDOT
Construction Cost: $35,000,000
Completion Date:  September 2009

Details
Cape Romain completed project

Replacement of Berth 8

Wilmington, NC
Owner:  North Carolina State Ports Authority
Construction Cost: $16,100,000
Completion Date:  March 2010

Details
Cape Romain completed project

Peninsula Trunkmain 1A

Charleston County, SC
Owner:  Charleston Water System
Construction Cost: $2,489,475
Completion Date:  December 2009

Details
Cape Romain completed project

US Coast Guard Range Towers

Charleston Harbor, Charleston, South Carolina
Owner:  United States Coast Guard
Construction Cost: $ 1,604,800.00
Completion Date:  November 2004

Details
Cape Romain completed project

Parcel E Bridge

Daniel Island, SC
Owner:  The Daniel Island Company
Construction Cost: $530,860
Completion Date:  February 2010

Details
Cape Romain completed project

Statewide Bridge Project

Jasper County, SC
Owner:  SC Department of Transportation
Construction Cost: $ 2,353,387.00
Completion Date:  February 2006

Details
Cape Romain completed project

Simmons Pointe Trip Wall

Mt. Pleasant, SC
Owner:  Simmons Pointe
Construction Cost: $924,000
Completion Date:  April 2011

Details
Cape Romain completed project

Rhodens Island Bridge

Daniel Island, SC
Owner:  The Daniel Island Company
Construction Cost: $3,017,000.00
Completion Date:  May 2010

Details
Cape Romain completed project

Folly Rd Bridge over Ellis Creek

Charleston, SC
Owner:  South Carolina Dept. of Transportation
Construction Cost: $ 5,496,336.00
Completion Date:  February 2010

Details
Cape Romain completed project

Prince Creek W. Connector Br.

Horry County, SC
Owner:  BEC II
Construction Cost: $2,475,021
Completion Date:  June 2006

Details
Cape Romain completed project

Harbor Town 18th Green

Hilton Head, SC
Owner:  The Sea Pines Company, LLC
Construction Cost: $483,875
Completion Date:  September 2011

Details
Cape Romain completed project

Plantation Harbor

Horry County, SC
Owner:  Paradise Basin of S.C.
Construction Cost: $584,000
Completion Date:  April 2010

Details
Cape Romain completed project

Driveway Bridge

Charleston, SC
Owner:  The Daniel Island Company
Construction Cost: $275,895
Completion Date:  April 2010

Details
Cape Romain completed project

Tides Condominiums Trip Wall

Mt. Pleasant, SC
Owner:  The Sidbury Group, LLC
Construction Cost: $1,042,900
Completion Date:  May 2007

Details
Cape Romain completed project

Lake Townsend

Greensboro, NC
Owner:  Seaside Environmental Company
Construction Cost: $3,300,000
Completion Date:  December 2008

Details
Cape Romain completed project

Harbor River Main Replacement

Beaufort County, SC
Owner:  Fripp Island Public Service District
Construction Cost: $472,207
Completion Date:  June 2011

Details
Cape Romain completed project

Park Island Bridge - Park West

Mt. Pleasant, SC
Owner:  Park Island Development, Inc.
Construction Cost: $ 4,439,648.00
Completion Date:  June 2007

Details